The short version
- A good quote is clear enough that the client cannot say "I thought that was included".
- List materials and labour as separate lines. Clients trust a quote they can read.
- Say which currency you charge in, and what happens if prices or exchange rates move.
- Say how long the quote is valid. Material prices change fast.
- Write what is not included. This stops most arguments before they start.
- Ask for a deposit, and agree the payment stages before you start.
Step 1: Visit the site and measure
Never quote from a phone call alone. Go to the site, measure, and take photos. Write down what you see: the state of the walls, access for trucks, where water and power come from. Ask the client what finish they want, because "paint the room" can mean a cheap coat or a full prep and two coats.
Make a simple list of the jobs, in the order they will happen. For a small house extension that could be: foundations, walls, roof, plaster, floor, doors and windows, electrical, painting.
Step 2: Work out quantities
For each job, count what you need: bricks, bags of cement, sand, roof sheets, pipes, paint. Add a little extra for breakage and waste. Many builders add around 5 to 10 percent for bricks, tiles and sheets, but use your own experience. Cutting and breakage on your jobs is the real number.
Step 3: Price materials and labour
Get current prices from your supplier on the day you write the quote. Ask for a written or WhatsApp price list, so you can show where the number came from. Then add labour:
- Labour: your workers' pay for the time the job takes, plus your own time.
- Transport: deliveries and trips to the supplier.
- Equipment hire: mixer, scaffolding, anything you rent.
- Permits and inspections, if the job needs them. Ask your local council what applies.
- Your margin: the profit and the risk. A job always has surprises, so do not price at cost.
Keep a note of your own costs for the job. When the job finishes, compare it to the quote. That is how you learn what to charge next time.
What every quote must contain
- Your business name, phone number and address. Add your registration or tax number if you have one.
- The client's name and the site address.
- A quote number and the date.
- How long the quote is valid, for example 14 days.
- A description of the work, in plain words, with measurements.
- Materials and labour, with a price for each line.
- The total, and the currency.
- What is included, and what is not.
- The payment stages and how to pay.
- The start date and how long the work will take.
- How changes are handled.
- A place for the client to sign and date to accept.
If you are registered for VAT or sales tax, show it as a separate line, and follow the rules of your tax authority on how a tax quote or invoice must look. If you are not sure, ask your accountant or your revenue authority. Do not guess.
Worked example: a two-room extension in Harare
This example is made up, but the numbers are realistic enough to show how the quote is laid out. Check every price with your own supplier before you use any of them.
Mr Moyo wants a 4 m by 5 m room added to the back of his house, with a corrugated sheet roof, plastered walls and a concrete floor. The builder visits on 12 November and sends the quote below.
| Item | Qty | Unit price | Total |
|---|---|---|---|
| Materials | |||
| Common bricks | 3,000 | US$0.10 | US$300.00 |
| Cement, 50 kg bag | 60 | US$11.00 | US$660.00 |
| River sand, per load | 3 | US$90.00 | US$270.00 |
| Roof sheets, 3 m | 20 | US$28.00 | US$560.00 |
| Roof timber, set | 1 | US$420.00 | US$420.00 |
| Door and window frames | 1 set | US$260.00 | US$260.00 |
| Materials subtotal | US$2,470.00 | ||
| Labour | |||
| Foundations, walls, roof, plaster, floor (3 workers, 3 weeks) | 1 | US$1,500.00 | US$1,500.00 |
| Transport and delivery | 1 | US$150.00 | US$150.00 |
| Labour and transport subtotal | US$1,650.00 | ||
| Total | US$4,120.00 |
The builder's own margin is built into the labour line and the unit prices. Some builders show it as a separate line instead. Both are fine, as long as you are consistent.
Payment stages
| Stage | When | Share | Amount |
|---|---|---|---|
| Deposit | Before work starts, to buy materials | 50% | US$2,060.00 |
| Second payment | Walls up and roof on | 30% | US$1,236.00 |
| Final payment | Work finished and checked with the client | 20% | US$824.00 |
If the client pays in ZiG
If you quote in US dollars but accept ZiG, write down the exchange rate you will use and when it is fixed. For example: "Payments in ZiG are accepted at the rate we agree on the day of payment, written on the receipt." The simplest way is to agree the rate each time.
Example: the deposit of US$2,060 is paid in ZiG on a day when you both agree on ZiG 26.50 = US$1. Then the client pays ZiG 54,590 (2,060 × 26.50). This rate is only an example. Rates move, so use the rate you both agree on the day, and say where it comes from.
Receipt: deposit for Quote Q-0031 Received: ZiG 54,590 by [bank transfer] on 20 November Agreed rate: ZiG 26.50 = US$1, so this pays US$2,060.00 Balance still to pay: US$2,060.00
If you are worried about prices rising during a long job, say so in the quote, for example: "Material prices are fixed for the quote's validity period. If prices rise by more than [10%] after the work starts, we will agree any change in writing before ordering." Choose a figure you and the client are happy with.
Free quotation template
Copy this into a Word document, a spreadsheet or a note on your phone. Change what is in square brackets.
[Your business name] [Phone] | [Address] | [Registration or tax number, if you have one] QUOTATION Q-[0031] Date: [12 November] Valid for: [14 days] Client: [Mr Moyo] Site address: [12 Example Road, Harare] Work: [Build a 4 m x 5 m room at the back of the house: foundations, brick walls, corrugated sheet roof, plaster, concrete floor, door and window frames.] Item | Qty | Unit price | Total Materials [Common bricks] | [3,000] | [US$0.10] | [US$300.00] [Cement, 50 kg bag] | [60] | [US$11.00]| [US$660.00] Labour [3 workers, 3 weeks] | [1] | [US$1,500]| [US$1,500.00] Transport | [1] | [US$150] | [US$150.00] TOTAL | [US$4,120.00] Included: [all materials and labour listed above, rubble removal] Not included: [electrical wiring, painting, ceiling, plumbing, permits and plans] Payment: [50% deposit, 30% when walls and roof are done, 20% when finished] Currency: [US dollars. ZiG accepted at the rate agreed on the day of payment.] How to pay: [Bank details / EcoCash / InnBucks / M-Pesa / Airtel Money / MTN MoMo number] Start date: [1 December] Time to finish: [about 3 weeks, weather permitting] Changes: Any extra work is priced and agreed in writing before we start it. To accept, sign and date below. Client signature: ____________________ Date: ____________
Mistakes that cost builders money
- Quoting from memory. Prices change. Check your supplier's price on the day.
- Forgetting transport, hire and waste. They are small each time but add up.
- Leaving out what is not included. If the quote does not say painting is excluded, the client may expect it.
- One lump sum with no breakdown. It is harder for the client to trust, and harder for you to defend when they ask for changes.
- No deposit. Without one, you are lending the client your money to buy their materials.
- Agreeing changes by word of mouth. Write every extra on WhatsApp, with the price, and get a "yes" before you do the work.
- Starting before the quote is signed. A reply on WhatsApp saying "I accept" also works, but keep it.
After they say yes
Send the signed quote back with a receipt for the deposit. Order the materials the same day while the price is still good. Keep every supplier receipt in one folder. When the job is done, invoice the final payment on the day. If it is paid late, our guide on chasing unpaid invoices politely has messages you can copy.
